40 Smart Grid Conference 2014 (SGC’14) - Grid Renovation Workshop
Illustrative DSO/DSP Use Case (Cont’ed)
• Forecast is for a hot day
• Load forecast within the load pocket
is large due to lots of air
conditioners expected to be on
• Feeders into the load pocket are at
expected at their capacity limit; net
load in load pocket exceeding import
capacity into the pocket by 5 MW
• The ESCO bids into the DSO retail
market (at $80/MWh) to have the
DSO serve any shortfall due to
potential load pocket import
limitations (the $80/MWh is
cheaper than the cost of running
the emergency generator.)
• CSP offers Aggregated DR from
within the load pocket into the ISO
market (at $60/MWh)
• There is a lot of solar generation
outside the load pocket
• Wholesale market prices (LMPs at
transmission substations) are
moderate ($40/MWh)
DA
ESCO Bid:
$80/MWh
Load
Pocket
DR
DR
DR
ISO
CSP Offer:
$60/MWh
DSO
LMP: $40/MWh